Mike Abbott - Engineering Manager Piletech
We hear incorrect assumptions, statements and perceptions
about screw piles a lot. The mythbusting
series of posts will hopefully educate you on the intricacies of screw
pile design and dispel some of those myths as loose accusations.
When I started working with screw piles 8 years ago I too
thought “there must be disturbance of the ground with that helix being
installed, mustn’t there?” I’ll jump
straight into the answer… “It could, but not with an experienced screw piling
specialist”. Key reasons why not are:
- True helix – pile manufacture
- Empirical evidence
- Soil displacement during installation
- Installation considerations
“That’s great in theory, but so what?” I hear the sceptics
say. It stands to reason that if there
was considerable ground disturbance in the material where the helix had
travelled you could expect to see an initial ‘take up’ of pile deflection,
under tension loading, at the toe of the pile in this weakened material. The tension load test results curve would
show a sudden rise at the initial low loads and then stiffen up as the ground
compressed above the helix…right? Well, Piletech
have performed over 500 load tests over the past 17 years that we’ve been
operating. Of these load tests, more
than 150 have been conducted in tension (pull up). Very few of the load tests (less than 4%) display this phenomenon. Almost all tests show instant tension take-up at the helix, because the true helix doesn't actually disturb the ground. Because Piletech undertake regular load tests, we conform to not only "best practice" but international standards. We know how our piles perform on each project.
Screw piles are a displacement pile with respect to the pile
shaft area. Piletech install an end cap
in the base of each pile, which pushes the ground material out around the pile
shaft during the installation process.
As such, close to the pile shaft you might actually expect to see a
densification of the material. Piletech has
carried out some field testing where shear vanes were performed prior to the
installation of a screw pile. The shear
vanes were then repeated in the path of the helix. The results showed a reduction only in the
top 0.5m of installation after which slight improvements to pre-installation shear
strength were measured. The disturbance
in the upper 0.5m is not usually an issue given that it is typically removed in
the formation of the pile caps or ground beams.
That is not to say that you cannot get disturbance if the
helix is manufactured poorly or if site conditions result in a pile not being
installed ‘on pitch’. A pile being
installed on pitch means that for each revolution of the pile it will progress
downwards by the pitch of the helix. If,
for some reason, the pile starts progressing at less than a helix pitch for
each revolution, such as an abrupt change in material properties, then there
may be some ground disturbance. This
should be monitored by the pile installer.
To show I’m not just making it up I have attached a load
test curve showing the displacement of a pile on loading. I have chosen a test performed on a shallow
pile to remove the argument that skin friction is masking the effect of initial
helix movement.
I was also searching for the answer but after reading your article my all doubts are clear.Thanks to you
ReplyDeletescrew piles
Nice article. Thanks for sharing.
ReplyDeletewhen simplest the quality screw will do. when and wherein to save on piling prices with screw piles.
We provide services of Besment waterproofing, concrete repair, footings, subsidence, basement underpin articles, basement walls, retaining walls, shoring, spray concrete, underpinning, grout injection, house underpinning(sydney), underpinning services, foundation repairs, basement garages, house restumping and ventilation sub-floor.
install screw piers