Wednesday, 9 December 2015

Myth 3: Screw Piles Can’t Provide Any Lateral Restraint

Michael Abbott - Engineering Design Manager

We hear incorrect assumptions, statements and perceptions about screw piles a lot.  The mythbusting series of posts will hopefully educate you on the intricacies of screw pile design and dispel some of those myths as loose accusations. 

We have identified recently that screw piles have not been considered at the early design phase on account of an assumption that screw piles would not be able to provide sufficient lateral support for the structure.  On several occasions now we have subsequently investigated screw pile options for those structures and determined that they could, in fact, provide the required lateral support.  Furthermore, the use of screw piles would have made it possible for the structural designers to lighten the structure overall.  The client would have been able to get the benefit of a faster, cheaper and cleaner piling solution as well as save cost in the superstructure.  How?
Let’s consider some lateral design basics:

  • When you try to push an object through a soil medium it offers resistance to that pushing force.  Generally, the more rigid and larger the surface area of the object, the more resistance to the push it will offer.
  •  A stronger soil will provide more resistance than a weaker soil profile.
  • Resistance to lateral load is generated both structurally and geotechnically.  Geotechnical capacity is generated from the pile moving relative to the surrounding soil, structural capacity is gained from the fact that the steel shaft of the pile doesn’t naturally want to bend and, when within its elastic range, wants to spring back to its original straight condition.
  • The geometry of the pile relative to structure, ie raked pile, can result in lateral restraint.

Given the above, I’m not going to argue that screw piles could compete with the lateral capacities of large diameter bored piles, as the effective surface area of the screw pile is less.  However, what I challenge designers to do is think about how the structure could be made more laterally efficient (see tips below), which will bring the overall cost of the project down, and will often get the lateral loads into a range where screw piles are an option.

Piletech use a range of pipe sizes.  Larger and stiffer pipe sections can provide greater lateral support.  We have successfully installed 406mmÆ and 457mmÆ CHS piles to achieve better lateral performance.  With these larger pipe sizes we have been able to offer as much as 500kN lateral resistance.  We also have some tricks up our sleeve to get even more capacity when required [see previous blog post here] We have completed dozens of structures around New Zealand now where our screw piles, in conjunction with foundation, are providing the necessary lateral capacity.

Figure 1: Example of lateral load test in progress

So, how can you drive efficiency into your structure through using screw pile foundations:
  • Consider passive resistance of the structures pile caps or ground beams in conjunction with the lateral capacity of the piles.
  • Consider the ductility of your structure including the piles, we can provide the lateral stiffness (kN/mm) of the screw piles to the structural designers.  There is potential to increase building period and reduce spectral shape factor.
  • Use fixity of the screw pile into the foundation beams to maximize structural capacity of the pile.
  • Where appropriate, consider raked piles to provide lateral support.
  • Lighten up your structure as much as you can.


Lateral design forms part of Piletech’s design package.  We use the software L-Pile to model the lateral response to shear loading and, where beneficial, back up that design with lateral load testing.  

Tuesday, 3 November 2015

The Golden Nugget: Why is our load test database so valuable?

Briar Fleming - New Business Engineer



From the outside it might seem like screw piling is reasonably straight forward.  Anyone who has tried it will attest to the fact that it is nowhere near as simple as it looks, and one of the key influencing factors occurs before you even arrive on site – the design of the piles needs to balance load carrying capacity (make the piles bigger and stronger!) versus being able to actually get them in the ground (make the piles smaller and more penetrable!).  This skill is something our specialist design engineers have honed over the many years we’ve been operating in this one field – and are now at a point where they’ve almost seen it all, having even installed screw piles into a coral reef in the Maldives. 

For clients we haven’t worked with before, load testing is an area that can cause confusion and we have written a post on load testing helping to de-mystify the various reasons why we sometimes suggest doing a load test (as it allows a more refined design meaning smaller or fewer piles on the project, thereby bringing the cost of the main piling works down), and other times why the risk profile dictates that a load test is highly recommended (the designer will want to prove a bearing capacity of the ground and the corresponding deflection of the pile).

However whether your project has load testing or not, by working with Piletech you are benefiting from something no other screw pile design company in New Zealand has.  It’s a tech-y name but it is an absolute golden nugget of our business and it is closely guarded.  It is our 17 year old Load Test Database.

To put it very simply, when designing piles you need to take into account the strength of the ground, the strength of the pile, and a factor that correlates the ground strength to the torque required to install the pile.  This ensures the pile won’t break or refuse prematurely whilst being installed to design ground strength.  An example of this correlation is shown in the graph at the end of this post, taken from the upcoming IPENZ Practice Note on screw piles.  This factor is variable and is dependent on the screw pile configuration, depth, and soil characteristics. When Piletech was being established in New Zealand (coming from operating in Australia), one of our five key mandates for best practice was to complete a load test for every project to obtain this correlation factor.  Now, having been in this business for so long, this database of over 1000 load test results often means we can determine this factor without needing to complete a load test. The years and years of experience installing piles gives the designers and an additional nuance giving the piles the best ability to penetrate through the ground. 


Again, it’s the balance between making the pile strong enough, whilst also able to penetrate that is one of the key areas that takes screw piling from being pure science, into the area of art.  This very valuable load test database cumulated over 17 years sits behind every design we undertake and gives the client confidence they are getting a cost effective and trustworthy foundation solution for their project – we’re not called the screw pile specialists for nothing.



Tuesday, 20 October 2015

Myth 2: Screw piles disturb the ground during installation adversely affecting tension capacity

Mike Abbott - Engineering Manager Piletech



We hear incorrect assumptions, statements and perceptions about screw piles a lot.  The mythbusting series of posts will hopefully educate you on the intricacies of screw pile design and dispel some of those myths as loose accusations. 

When I started working with screw piles 8 years ago I too thought “there must be disturbance of the ground with that helix being installed, mustn’t there?”  I’ll jump straight into the answer… “It could, but not with an experienced screw piling specialist”.  Key reasons why not are:
  • True helix – pile manufacture
  • Empirical evidence
  •  Soil displacement during installation
  • Installation considerations
A screw pile, if manufactured correctly, should have a ‘true helix’.  You can refer to Piletech’s "True or Screwed" on this issue.  The true helix is manufactured with a constant change in pitch over its 360o travel around the pile, and always extends perfectly perpendicular to the pile shaft.  The true helix threads through the soil profile, much like a wood screw, rather than auguring or disturbing it. Manufacturing a true helix is more than an “art”, and requires precision engineering equipment, and experience.  It also requires more than “trust” that the manufacturer will supply a product that conforms to the designer’s specifications. Piletech have sole-supplier agreements with our helix manufacturer that extend over 15 years, for which QA has been consistently outstanding.

“That’s great in theory, but so what?” I hear the sceptics say.  It stands to reason that if there was considerable ground disturbance in the material where the helix had travelled you could expect to see an initial ‘take up’ of pile deflection, under tension loading, at the toe of the pile in this weakened material.  The tension load test results curve would show a sudden rise at the initial low loads and then stiffen up as the ground compressed above the helix…right?  Well, Piletech have performed over 500 load tests over the past 17 years that we’ve been operating.  Of these load tests, more than 150 have been conducted in tension (pull up).  Very few of the load tests (less than 4%) display this phenomenon.  Almost all tests show instant tension take-up at the helix, because the true helix doesn't actually disturb the ground.  Because Piletech undertake regular load tests, we conform to not only "best practice" but international standards.  We know how our piles perform on each project.

Screw piles are a displacement pile with respect to the pile shaft area.  Piletech install an end cap in the base of each pile, which pushes the ground material out around the pile shaft during the installation process.  As such, close to the pile shaft you might actually expect to see a densification of the material.  Piletech has carried out some field testing where shear vanes were performed prior to the installation of a screw pile.  The shear vanes were then repeated in the path of the helix.  The results showed a reduction only in the top 0.5m of installation after which slight improvements to pre-installation shear strength were measured.  The disturbance in the upper 0.5m is not usually an issue given that it is typically removed in the formation of the pile caps or ground beams.
That is not to say that you cannot get disturbance if the helix is manufactured poorly or if site conditions result in a pile not being installed ‘on pitch’.  A pile being installed on pitch means that for each revolution of the pile it will progress downwards by the pitch of the helix.  If, for some reason, the pile starts progressing at less than a helix pitch for each revolution, such as an abrupt change in material properties, then there may be some ground disturbance.  This should be monitored by the pile installer. 

To show I’m not just making it up I have attached a load test curve showing the displacement of a pile on loading.  I have chosen a test performed on a shallow pile to remove the argument that skin friction is masking the effect of initial helix movement.



So – does a screw pile disturb the ground during installation adversely effecting tension capacity?? … “It could, but not with an experienced screw piling specialist”.


Wednesday, 10 June 2015

Mythbusters - applications of screw piles

Mike Abbott - Engineering Manager Piletech









This post is the first in a series of mythbusting queries about screw piles.  We hear incorrect assumptions, statements and perceptions about screw piles a lot.  The mythbusting series of posts will hopefully dispel some of those myths as false accusations.

For many years people in the construction industry have viewed screw piles as petite little piles that only go under residential or light commercial structures.  10 years ago I may have been inclined to agree with that sentiment, but a lot has happened in that time to the point where we have just completed a tension load test on a screw pile to 3250kN; that’s 325 tonnes.

So what has had to change to achieve huge capacity improvements?  The answer is simpler than you might think; nothing really.  Our design philosophies haven’t changed, we have merely up-sized each component in the system.  Larger excavators driving larger power-heads, driving larger diameter and thicker walled pipe driving larger diameter helices into denser ground.  The sum of all of those equates to pile capacities in excess of 4000kN in compression and 3250kN in tension.

Whilst Piletech are not in the business to make and break records, we expect that this will be a world record for tension capacity of a screw pile.  Perhaps if anyone out there has information to the contrary they can let us know.  We would like some further motivation to test to greater heights.

Tuesday, 19 May 2015

Why load test?

William Brown - New Business Manager




What is a load test? Why do we do them? Why do we sometimes recommend not doing them?


A load test is where a pile is installed on site and loaded to prove how much it compresses or stretches as load is applied. Piletech has performed hundreds of load tests over the last 16 years as a means of proving our system, particularly in the early days. In the process we have built up a large load testing database, which is a unique resource when designing piles for new projects across New Zealand. Used in conjunction with a site specific geotechnical investigation the load test database allows us to predict pile performance using real data before we ever set foot on site, producing designs that are cost effective and reliable.

Although there are costs associated with load testing, in many cases it can reduce the overall cost of the project. When considering 'to test or not to test' it pays to understand the benefits of testing, the programme implications, how this feeds into the consenting process and how it can change a pile design.

Engineering design is all about making a calculated assessment of each design element. In the absence of testing, a conservative design approach will be adopted. However, when we load test the amount of information that we have about a site increases, which in turn increases the confidence that a designer has about the soil properties and allows a more refined pile design. Generally this means that when a load test is carried out, lighter piles can be used, with less steel required.

It then becomes a question of economics. On a large project, economies of scale can be gained through refinement of the design - that is, the savings that can be made are greater than the cost of the testing. On smaller projects the opposite is true - in this case we would generally recommend that testing is not undertaken and a more conservative design approach is used. This results in heavier, more expensive piles, but a lower cost and faster construction programme overall.

Want a bit more detail? If so, read on...


All structural components of a building will experience some movement, or 'deflection' as they are loaded. Load testing consists of installing a test pile, usually before the main works, then applying weight to, or pulling on that pile and measuring how far it will compress or stretch as it is loaded.

The goals of the load test are twofold. Firstly, we want to prove that the pile can carry the load that the building will place on it, in the ground that is present on site. Secondly, we want to show the relationship between load and deflection - how much the pile will compress or stretch under a given load, and check if this is within acceptable limits.

Pile load tests need a large amount of 'reaction' - the opposite force that is required in order to push the pile to its limits. For small tests this can sometimes be provided using a kentledge system of weights, or even by using the excavator that installed the pile for dead weight. However, more often a system of 'reaction piles' is used - typically 2 - 6 piles installed in a grid around the test pile, connected with steel beams. Hydraulic jacks are used to apply pressure to the test pile in pre-determined increments, and the deflection of the pile head is measured and plotted on a graph.

Typical Load Test Curve


All of this takes time and can be a significant cost to a project, so why do it?


Structural design in New Zealand is carried out using a system called 'limit state design'. Basically this means that engineers work out how much a building weighs and how big structural components such as piles need to be to carry that weight. They then apply safety factors to scale up the assumed weight of the building and scale down the assumed strength of a given component, so that the chances of any component being overloaded are very small.

For piles, typical 'strength reduction factors' range from 0.4 to 0.7. By way of example, if calculations tell us that a pile can carry 100 tonnes, and we use a strength reduction factor of 0.4, this means that even though the pile can carry 100 tonnes before it is considered to have 'failed', we will only assume that it can carry 40 tonnes for design purposes. In other words, that pile has 60 tonnes of reserve capacity.

So here is where load testing can save you money.


On a project where we don't do a load test, we need to use a conservative factor of say 0.4 - 0.5, like in the example above. On a project where we do perform load testing, we are getting site specific information, which increases the confidence level of the design. When we load test, the factor can be increased to as much as 0.7, depending on the site and other considerations. This means that the same pile used in the example above is now assumed to carry 70 tonnes, or nearly twice what it did in the first example.

The same pile, carrying almost twice the load.


Assuming that we have been involved early enough in the process, this allows us to work with the structural engineer to optimise the design, reducing the cost of the foundation and potentially saving time on site. The large database of load testing that Piletech has compiled over the last 16 years means that we are often able to predict load test results before carrying them out, and in doing so drive this design refinement process further forward in the design programme. In this scenario the load test simply verifies design assumptions and is a happy medium between absolute refinement of the design and balancing the programme requirements of a design and construction process.

For more information on how helpful Piletech's load test database can be, watch this space for an upcoming blog. In the meantime, we'd love to have a one on one discussion about how this can benefit your next project.





Tuesday, 21 April 2015

Pulling in the same direction

James Wood - Piletech Manager



























Over the years we have worked for many clients with a variety of strategies and cultures for procuring their trades; from the hard money, nail the sub-contractor through to collaboration and early specialist involvement or nominated sub-contracts.

However, all 1000 plus of these screw pile specific projects have been lump sums - they provide only so much room to drive collaboration and best-for-project outcomes.

2015 is seeing a new opportunity for Piletech with us being part of an Alliance Contract.
An Alliance Contract can be defined as an agreement between two or more parties to achieve agreed outcomes on the basis of sharing risk and reward.

In this model we are open book on cost and work towards an agreed target outturn costs (TOC), where all parties take a pain gain share in the final outcome. In essence, you sink or swim together, which ensures that all parties do what is best for the success of the project.

The transparency of the contract and the trust and collaboration that this affords, has allowed our specialist knowledge to be leveraged to best effect. The key benefits are:

  • Coordinated Design - achieved through early involvement, which has reduced the geotechnical risk and ensures all design drivers are identified and managed upfront;
  • Optimised Budget – early testing on site gained early, detailed understanding of the ground. The TOC was then developed which was assessed by an independent Engineer;
  • Efficient Procurement - materials are procured specifically for project, saving significant $ through optimising the supply chain. Steel will arrive just in time (JIT);
  • Early detailed Methodology – planned as part of the TOC, and optimised in parallel with the supply chain.

The project requires significant screw piling, certainly the largest scope in New Zealand and approaching some of the largest we have seen globally. This model may not be practical for smaller projects with clearer initial scope and risks, it will certainly provide us with experiences and lessons that we can leverage into the traditional business.

It’s an interesting journey we are embarking on that already has already seen many positives - We look forward to the lessons we will learn.



Tuesday, 3 March 2015

Look Before You Leap

William Brown - New Business Manager


In New Zealand we’re lucky to enjoy a wide variety of outdoor environments – mountains of rock forced up by earth movement, ancient forests, rocky rivers carrying stones and sand onto open plains, wetland areas, sandstone cliffs and beautiful sandy beaches. As much as we like to get out in these environments, we also like to build in them, and the ground beneath our feet can be as varied as the view from above.

If you’re building, you will probably be expected to get a geotechnical report, but how do you know that your report will be enough to design the foundation that holds up your building, and minimise the chance of nasty surprises (and hidden costs) when you start building?

Something that we often see when a customer first makes contact is that their current geotechnical investigation isn’t detailed enough to design deep foundations, and more investigation is needed. Often this is a valid approach – geotechnical investigation can be quite an iterative process and the first round of investigation often focuses on shallow foundations – why would you look deep if you don’t need to? However, often the need for additional investigation comes as an unplanned expense and time delay, which people could do without. Choosing a geotechnical engineer who is familiar with local conditions can be helpful to reduce surprises in this area, as they may have an idea of what foundation types have worked in your area in the past.

So why bother with the additional investigation?

The simple answer is so that you know what you’re dealing with before you start building. Is that ‘hard’ layer 7 metres below the surface strong enough? Is it thick enough? Does it vary in depth and thickness across the building site, or does it disappear altogether? Will the ground liquefy in an earthquake? Just as rivers meander across the ground, conditions underground can vary from one side of a building to the other. Other times the ground beneath can be quite consistent. Although a geotechnical investigation is only ever an indication of what lies beneath, the more information you have the clearer this picture becomes.

At Piletech, we’re happy to work with your geotechnical engineer to make sure the right information is gathered, saving you time and money, and helping you to identify what lies beneath so that you can plan this into your build.

Wednesday, 4 February 2015

Can piles founded in the intermediate gravel layer in Christchurch perform to your specification? Don’t punch above your weight!

By Mike Abbott

For those unfamiliar with Christchurch geology, Christchurch is underlain with relatively recent alluvium deposits with substantial variability of the layered strata.  Among these, there is often a dense, competent and non-liquefiable gravel layer, which is often viewed as an attractive option for piling.  Clear commercial advantages exist by founding in an intermediate gravel layer as this will be a cheaper piling option over founding piles in the Riccarton Gravel layer that are considerably deeper.  But will this layer offer the appropriate pile response required by the structure and the specification?  What considerations need addressing to ensure a shallow piling option is appropriate?  


Diagram 1: sketch of typical geology of an intermediate layer in the Christchurch region.

Firstly, the specification should identify design loads for all loading combinations as well as providing acceptable deflection criteria.  NZS1170:2002 provides information on serviceability and ultimate loading combinations.  A load case that is often overlooked is the post seismic static load case 1.2G + YQ + Su, where Su is 1.2 times the potential negative skin friction that may act as a result of settling ground following a seismic event.
Acceptable deflections will vary from structure to structure, potentially even varying within different parts of a structure.  Generally, it is the Structural Engineer who will determine the deflection criteria required to protect the superstructure.  In the absence of specific criteria, AS2159:2009 Piling Code provides a set of default deflection criteria based on pile type and size.
Once these criteria are established, it must be determined whether the intermediate gravel layer can provide the necessary strength and resistance to pile deflection.  Factors contributing to pile deflection may include:
  • Elastic shortening of the pile shaft
  • Structural deformation of the helix
  •  Geotechnical deformation of bearing strata
  •  Liquefaction induced geotechnical settlement of underlying layer
It is the punching of piles into the lower strength underlying layer (as shown in Diagram 1) that is often not considered.  It is also this factor that is most likely to determine the sufficiency of the intermediate layer to provide the required bearing and deflection performance.  Punching into a liquefiable material cannot be determined by load testing as the weaker material underlying the intermediate layer will not be in its liquefied (weaker) state during testing.  Therefore, numerical analysis and modelling is the only way to justify using piles in intermediate layers. 
We generally consider an elastic stress analysis (Boussinesq 1885) ensuring that the thickness of competent material is sufficient to ensure stress at the interface with any weaker layers is less than the weaker layers capacity.  Determination of the ground strength of liquefied sand can be estimated using equations developed by Stark and Olsen (2002) detailed in their paper ‘Liquefied strength ratio from liquefaction flow failure case histories’.

The following links may be of interest relating to this article:
  •  Available on our website is a video showing the effects of load bearing piles on a dense layer overlying a weaker sub-layer HERE. 
  •  Geotechnical interpretive report for the Christchurch CBD area HERE.