By Rodney Appleby, New Business Manager
PART II: The stuff you can't touch....
Often in the feasibility stage the pros and cons of bored piles vs timber piles vs UC piles vs pad foundation get weighed up and compared. Ultimately, the decisions we make have to work on a technical level… and then be economically viable.
Piling can literally be as easy as drilling a hole and
filling it with concrete! But the times it’s not that easy (aka 99% of the
time), if you’ve not done your homework, and you chose the wrong technique, you
will be riding the horse of pain off into a lonely sunset.
Let’s say you had decided bored piles were the way to
go… But did you consider screw
piles? And why, or when, would a screw
pile be your best option?
DESIGN:
This is one of the
FIRST areas to assess whether screw piles are an option. If they can take the loads on the building,
then it’s definitely worth further investigation.
We have load
tested our screw piles to achieve:
·
Over 4000kN axial
·
Over 3,250kN tension, and
·
Up to 400kN for lateral loads… (with a shear key
this can rise to over 650kN..)
Higher loads still!….. Just install 2 for 1 screw:bored
piles… Or 3:1… Often it will still be cheaper!
Screw pile designs are taking much bigger loads
now. Ask the experts…
PROGRAMME:
I’ve completed a rough programme graph comparison below
between a screw pile operation and a LDA (Large Diameter Auger) bored pile…
it’s dependent on ground conditions, access, and plant mobility. I’ve assumed the bottom 2m is into competent
material, and that access is relatively easy, and includes mobilisation time.
I think the graph speaks for itself.
So a longer
programme will effect pricing in two ways:
·
The cost of all piling plant and labour on a
bored piling job is typically $3-4k/day more than that of a screw piling
project… So every extra day really hurts the bottom line.
·
P&G costs go up.
Screw piling is much much quicker – and this
results in cost savings!
ENVIRONMENTAL
& TMP:
Pile arisings, spoil, dirt, crap… Whatever you call it, it
needs to get off site. Erosion and
sediment control is a major with wet surfaces.
It gets into drains and tracked out on to the road. Silt fences, wheel
washing (man + waterblaster), and traffic management all cost more money.
Contaminated spoil… New Work Safe H&S rules state the
client, consultant and contractor need to be actively managing this. Tip fees,
additional PPE, handling, cartage all cost more money.
If you don’t manage these the council shut your site down,
with fines and even convictions!
Screw piles = no spoil = no ground water = no
silt controls = no potential environmental incident.
Screw piles = no spoil = no unforeseen
contamination variations = no H&S incidents.
Screw piles = less supply trucks + no spoil =
no wheel-washing = less TMP $$ & no potential incident
NOISE & VIBRATION:
Large casings require vibro-hammers. They’re very noisy and
can often be felt hundreds of metres away from the site. This could not only result in complaints from
neighbours but may be even a few cracks that neighbour “never noticed before”. Dilapidation surveys can cost around $1-2k
per house. Hopefully the complaints don’t temporarily shut the site down.
Watch out the Contractor doesn’t charge extra to reduce noise
because of a methodology change!
Screw piling is often the pile of choice in the electricity
world because vibration monitors placed on the transformer never know we were
there!
Screw piles = low noise = next to no vibration
= no dilapidation surveys = no noise complaints = reduced risks to your
project.
-
So hopefully by now you’re starting to get to thinking that
you’ve got nothing to lose by asking Piletech to give a free Rough Order Cost
to see if they’re within the ball park of your current bored pile design.
FYI: Make sure you read “Bored? Why Not Screw? Part I: The stuff youcan touch”