Monday 12 September 2016

HAMMERED??? WHY NOT SCREW? Part 2

HAMMERED??? WHY NOT SCREW?

by Rodney Appleby, New Business Manager

PART II: The stuff you can’t touch…

Often in the feasibility stage the pros and cons of bored piles vs timber piles vs UC piles vs pad foundation get weighed up and compared.  Ultimately, the decisions we make have to work on a technical level… and then be economically viable.

Piling can literally be as easy as drilling a hole and filling it with concrete! But the times it’s not that easy (as in 99% of the time), if you’ve not done your homework, and you chose the wrong technique, you will be riding the horse of pain off into a lonely sunset.
Let’s say you had decided driven UC piles were the way to go…  But did you consider screw piles? And why, or when, would a screw pile be your best option?

DESIGN: 
Are there tension loads?  With a UC – forget about it!  Screw piles can embed themselves into hard layers, and, with a big helix at the base, generate their capacity through end bearing.  This allows us to generate much higher loads, especially in tension.
End-bearing or skin friction?  UC’s have a very small area on which to bear, so it needs to be “rock solid”.  Skin friction as a means of generating capacity is less reliable and can require horrendously deep piles to achieve the desired loads, particularly if there are liquefiable layers. 
This is where a screw pile comes into it’s own!  Is there an intermediate hard layer? Often this layer may not be enough to provide adequate end bearing using a UC – but with a significantly larger bearing area that a large diameter helix offers – suddenly you may be able to halve the length of the piles – thereby reducing material cost as well as installation time.
And if the soil is absolute poop then think about multiple helices.  We’ve put up to five 900Æ helices on a pile shaft to help found our piles at a shallower level.  You can’t do that with a UC!
Screw piles = potential to found on intermediate layers = multiple helices = massive cost savings.

TESTING:
A typical driven UC specification will require a percentage of piles to be Pile Driver Analyser tested – otherwise known as PDA testing. This costs money and it takes time, and a lot of lazy contractors will tag out of it, stating they’ll check their pile capacities with the Hiley Formula…. see “rough guess for pile capacity calculation!”  The designer re-asserts PDA is required… see time delay… see variation.
Sometimes soils work in mysterious ways, and pile heave is not uncommon. Did you also make sure that the contractor re-hit his piles 24hrs after achieving the set? 
Screw piles can factor the cost of a static load test at the start of a project to give everyone certainty.  We also have strong correlations between the torque applied to a pile and it’s pile capacity.  Piletech record torque readings for every pile, which are reviewed by our Chartered Professional Engineers.
Screw pile testing is completed upfront or during the project without delays – no hidden extras.

NOISE & VIBRATION:
This really is a no brainer.  If you’re driving UC’s you’ll be hearing the “ping” for miles and feel the shudder beneath your feet…. This could not only result in complaints from neighbours but maybe even a few cracks pop up that the neighbour “never noticed in my house before”. Dilapidation surveys can cost around $1-2k per house. Hopefully the complaints don’t temporarily shut the site down.
Watch out the Contractor doesn’t charge extra to reduce noise because of a methodology change!
Is your project in a school? Kindergarten? Hospital? Oil & Gas? Screw piles are the pile of choice in the electricity world because vibration monitors placed on adjacent transformers don’t know we’re there! 
Screw piles = low noise = next to no vibration = no dilapidation surveys = no noise complaints = reduced risks to your project…. AND NO HEADACHES!

QUALITY:
Did you ever hear the story of a contractor who drove UC’sthat lost their verticality? the UC essentially followed a “U” shape, and came back up, across the road – and pushed up a car!!!  The ability to control inclination, correct it, and monitor it is not easy, nor cheap.
Conversely, our record screw pile is to a depth of 48m.  We’d go deeper – but we hit the hard stuff and didn’t need to.  We regularly go 40+ metres without issues.  The true-helix keeps the pile on course, and with an open pipe you can tell if our pile lost verticality.  Good luck with that on a UC!
Screw piles = better quality control.
-
So hopefully by now you’re starting to get to thinking that you’ve got nothing to lose by asking Piletech to give a free Rough Order Cost to see if they’re within the ball park of your current bored pile design. 


Thursday 1 September 2016

HAMMERED??? WHY NOT SCREW? Part 1


HAMMERED??? WHY NOT SCREW?

By Rodney Appleby, New Business Manager

PART I: The stuff you can see and touch.

Often in the feasibility stage the pros and cons of bored piles vs timber piles vs UC piles vs pad foundation get weighed up and compared.  Ultimately, the decisions we make have to work on a technical level… and then be economically viable.

Piling can literally be as easy as drilling a hole and filling it with concrete! But the times it’s not that easy (as in 99% of the time), if you’ve not done your homework, and you chose the wrong technique, you will be riding the horse of pain off into a lonely sunset.
Let’s say you had decided driven UC piles were the way to go…  But did you consider screw piles?  And why, or when, would a screw pile be a superior option?

MATERIALS: 
A pipe compared to UC’s ($/m) – it’s relatively similar. 
The key ingredient here is lead time!  If you’re doing a big job, to keep the costs down, you’ll have to order from China, Indonesia, Korea… wherever… but the Contractor will always tag a 3 month lead time before they can start.  If it’s a smaller job, then they might buy it from Fletcher EasySteel off the shelf, but then you’ll be paying a much higher rate.
Technically, the same thing applies to screw pile pipe…. unless you’re Piletech… Piletech holds between $2M-$3M worth of stock (both pipe and plate) in our yards so that we can turn on a dime, and get your project started – whilst keeping costs low because we bought in bulk some time ago.
Piletech Screw piles = less lead time + cost savings.

BIGGER PLANT = BIGGER $$$: 
For small piles the plant will be similar.  But deeper piles with larger loads require larger drop hammers and leader frames, or vibro-hammers, and a crawler crane.  This means:
·         More upfront costs – as crawler cranes cost between $10k-$30k to mobilise,
·         Take 1 day to mobilise and 1 day to demobilise,
·         Cost around $2-4k per day more than typical screw piling plant, (considering all site plant and labour).
·         Reduce the area available on site, so no room to “swing the arms” safely, and thus…..
·         Piling productivity will drop. We regularly install 10-20 piles a day to 24m, and would estimate being 20-30% quicker than similar length driven UC’s.
o   Note: each day more = another $2-4k the client will have to pay for.
Cranes and leaders typically costs more per day than screw piling, with more “one-off” costs.

THE FOOTPRINT
Crawler cranes and leaders?  On a small site even turning becomes an issue.
Screw piling plant is smaller, quicker, nimbler, easier, and safer!!!

ENVIRONMENTAL & TMP:
Often contractors will pre-drill a starter hole to help stand the UC’s upright.  If so, make sure you’ve allowed to handle the spoil, and cart it off site.  Erosion and sediment control is a major with wet surfaces.  It gets tracked out on to the road, and into drains. Silt fences, wheel washing (man + waterblaster), and traffic management all cost more money.
Contaminated spoil… new Work Safe H&S rules state the client, consultant and contractor need to be actively managing this. Tip fees, additional PPE, handling, cartage all cost more money.
If you don’t manage these the council shut your site down, with fines and even convictions!
Screw piles = no spoil = no ground water = no silt controls = no potential environmental incident.
Screw piles = no spoil = no unforeseen contamination variations = no H&S incidents.
Screw piles = less trucks + no spoil = no wheel-washing = less TMP $$ & no potential incident

CONNECTION DETAILS:
Another potential hidden killer.  Piling contractors often tag out of cutting the piles to height, and then welding nelson studs, or top plates on.  At $200-$500 per pile – this will chew a hole in your profit if not allowed for. 
Screw piles typically have a few bits of rebar coming out of the pile which are concreted in.  No sweat, and allowed for in our costs.
Make sure you allow for connection costs when comparing apples and pears.

So hopefully by now you’re starting to get to thinking that you’ve got nothing to lose by asking Piletech to give a free Rough Order Cost to see if they’re within the ball park of my driven UC pile design. 
Tune in soon for “Hammered? Why not Screw? Part II:  The stuff you can’t touch...”